Information and updates on the construction of the new YCMES Campus...

The Main College Building is set to open in mid-June 2008 to house all classrooms, academic offices, administrative offices, the library, the cafeteria, and a conference/lecture hall.

Timeline:

May 10, 2008: Fourth floor ceiling is completed. 

May 1, 2008: Third floor interior is completed.

April 30, 2008: First and second floor interiors are completed. 

March 26, 2008: Third floor "Qamariya's" (decorative stained-glass windows) are installed.

March 23, 2008: Four floor construction begins on new campus building.

March 23, 2008: Two-story dining hall building construction is completed.

March 20, 2008: Third floor is completed with ceiling on new campus building.

March 3, 2008: Construction begins on Guest House premises for two-story dining hall and new kitchen.

February 3, 2008: Old Building is completely demolished.

January 20, 2008: Construction begins on adding third floor.

January 2, 2008: New sewage line is finished.

December 7, 2007: Foundation of main building is re-enforced.

November 28, 2007: Old building is demolished as it was structurally unstable. 

October 7, 2007: Construction begins

October 1, 2007:  Deed signed over to the Yemen College of Middle Eastern Studies

 

Construction Pictures:

back of center building, may 8, 2008front of center building, may 8, 2008

center building, 4 stories, back and front (may 10, 2008)

 

applying concrete to the steps of the 5th floor, may 10, 2008fourth floor, may 10, 2008

ceiling of fourth floor (may 10, 2008)                                                                    applying concrete to the steps (may 10, 2008)            fourth floor (may 10, 2008)

first floor (offices)  interior completed, may 10, 2008second floor (classrms) interior completed, may 10, 2008finishing the walls of the third floor, may 10, 2008   

first floor interior completed (may 10, 2008)                    second floor interior completed (may 10, 2008)                finishing the wall of third floor (may 10, 2008)

 

 

 

Prior to Construction: